853

news, views and issues around Greenwich, Charlton, Blackheath and Woolwich, south-east London – what you won't read in Greenwich Time

Posts Tagged ‘simon hughes

Greenwich and Woolwich foot tunnels: Did council lie over works?

with 7 comments

Greenwich Council told a Government agency that the unfinished Greenwich and Woolwich foot tunnel works had been completed, a minister has said, even though it now admits the tunnels are in a poor state of repair.

The project, which has been beset by delays, remains unfinished after the contractors were sacked last year, and last month Greenwich Council commissioned an independent investigation into what went wrong.

But local government minister Mark Prisk told Bermondsey MP Simon Hughes that Greenwich Council said the works, which had been funded by an £11.5m grant, had been finished – and any further work would have to come from the council’s own funds.

The cash was awarded by the Department for Communities and Local Government in November 2008. But the project moved to the Homes and Communities Agency, which took charge of monitoring progress on the project.

In a written response to the Liberal Democrat MP, Mr Prisk said: “The borough confirmed that all eligible works funded by the Homes and Communities Agency were completed as per the conditions of contract and that any remaining works would be funded from their own resources.”

However, contractors Dean & Dyball, Hyder Consulting and Swett were sacked in December 2011 following slow progress on the project, with the council issuing a series of misleading and evasive answers about the project until it finally owned up to the problems four weeks ago, and announced plans to take legal action against the firms.

The funding letter, signed by Greenwich’s assistant chief executive John Comber (and obtained by this website under the Freedom of Information Act), outlines the schedule of works.

It’s clear to anyone who uses either tunnel that the works are nowhere near finished – only the lifts and south rotunda in the Greenwich tunnel have been completed, along with the stairwell in the Woolwich tunnel. Greenwich Council refuses to publicly discuss what hasn’t been completed for fear of inflating new tenders to finish the work.

It’s also worth recalling Greenwich cabinet member Denise Hyland’s answer at a council meeting when asked, bluntly, if the Government’s money had run out.

“The budget is considered sufficient to complete the project, subject to the contractual issues being resolved with the contractors involved in the first phase of the works,” she said, despite the fact the council had claimed the works were completed and all the money had been spent.

I’ll leave it down to you to decide whether that, in retrospect, was a misleading answer. Incidentally, Greenwich has still not announced who will lead its investigation into the foot tunnel fiasco, and other big projects.

Whether or not the council misled the HCA – it’s certainly clear the government agency wasn’t taking enough notice of what was happening with its money.

To make matters more complex, the HCA’s functions in London were taken over by the mayor’s office earlier this year, which now means the responsibility for keeping track of the grant falls to a certain Boris Johnson, who has consistently batted away requests that he put pressure on Greenwich to finish the project. City Hall may now have to sit up and take more notice of what’s going on beneath the Thames.

Follow

Get every new post delivered to your Inbox.

Join 501 other followers